|
Carter
v Sherburne
Vermont S. Ct. [1974]
Author:- Sam
Biers
Relevant
Facts: Contractor brought action against owner to recover for
labor and materials furnished under written construction
contracts and for further amounts on quantum meruit basis for
labor and materials furnished without express agreement as to
price. Df was a developer builder, Pl a contractor.
The parties executed four contracts between them. The Ks
called for weekly progress payments based upon work completed w/
a provision for retaining 10 % until ten days after final
acceptance. Df kept shifting Pls activities from 1 k
to another and delaying payments to Pl. Dfs
representatives promised the Pl extensive additional Ks in return
for certain work building a gondola lift line w/o compensation.
Df notified Pl in April that no more progress payments would be
made on the gondola K. Pl continued work but did not finish.
The Ks were terminated in June.
Legal
Issue(s): Whether time was of the essence of the contracts and
contractor's failure to perform within time specified precluded
recovery, and that where parties had entered into an express,
although unformalized, contract for good consideration for work
in addition to that covered by contracts, contractor could
recover in quantum meruit for the additional work?Courts
Holding: No not of essence, and Contractors failure did not
preclude recovery; Yes QM.
Procedure:
Tr. Ct. rendered judgment in favor of the contractor and
the owner appealed. S. Ct Affirmed.
Law
or Rule(s): Where parties have not expressly declared their
intention as to whether time is of the essence of a contract,
determination as to whether time is of the essence depends on
intention of parties, circumstances surrounding transaction and
subject matter of the contract. Where time
is of the essence of contract, performance on time is a
constructive condition of the other party's duty, usually the
duty to pay for the performance rendered. Generally time is not
of the essence in a building or construction K in the absence of
an express provision.
Court
Rationale: Time was not of the essence in any of
these Ks. None of the four Ks included express language
making time of the essence, and there is nothing in the
circumstance surrounding these Ks. 2 Ks called for
completion dates and forfeitures for noncompliance but this does
not make time of the essence. Where time is not of the
essence a failure to complete work on time w/i a specified time
will not terminate a K, but will subject the contractor to
damages for the delay. Here the Dfs actions in
shifting the Pls activities and withholding payment caused the
delays. Df informed Pl in April that no more progress
payments would be made on the gondola K. At that time Pl
had completed a substantial portion of the work, but had not
invoiced it yet. Dfs notice concerned only the progress payments,
and was not a termination of the K. Failure of payment does
not require cessation of performance. Termination w/o legal
justification entitles the Pl to recover the K price for work
done before termination, or the reasonable value of the
performance rendered, QM.
Plaintiffs
Argument: The delays were a result of the Df, and the work was
performed.
Defendants
Argument: The Pl is not entitled to recover for work done after
notice, and Pl was not in substantial compliance w/ the Ks.
|