|
Groves v. John Wunder
Co.
Supreme Court of Minnesota, 1939.
Author: Jim
Facts: ? contracted with D where D leased
the land of ? and agreed to remove the sand and gravel. D
willfully breached the K by removing only the best gravel and
leaving the rest on the land. It was determined that it
would cost ? $60,000 to complete the project but the increased
value of the property of ? will only be $12,160.
Procedure: The trial court awarded ? only
$15,000 (increased value of property + interest). P, being
unhappy with the judgment, appeals.
Issue: Can ? recover for the cost of
completing the project even if it is more than the increased
value of the property?
Holding: Yes
Rationale: The D willfully breached
the K and he should not be awarded. According to the court,
the increased value of the property should not be a consideration
in the current case. Suppose a contractor were suing
the owner for breach of a grading K such as this. Would any
element of value, or lack of it, in the land have any relevance
in reckoning damages? Of course not.
Furthermore, awarding the ? the higher amount will not unjustly
enrich him. There is no unconscionable enrichment when the
court gives to one party what the other party had already
promised to give under the K. Reversed and remanded.
|