|
Austin
Instrument, Inc. v. Loral Corp.
Court of Appeals of New York, 1971.
29 N.Y.2d 124, 324 N.Y.S.2d 22, 272 N.E.2d 533.
(economic duress)
Author: Judd Bean
Statement of
Case:
*An action of
breach of contract involving a radar components supplier against
a radar supplier to the military for payment due upon the second
subcontract.
*An action of
coercion and breach of contract involving a radar supplier to the
military against a radar components supplier for damages to the
aggregate of the price increases under the first subcontract on
the ground of economic duress.
Facts:
(DURING VIETNAM)
Loral got a
contract to make some radar stuff for the Navy. They
subcontracted to Austin to produce about half of some required
precision gear components. When they got another Navy
contract, Austin bid again and wanted to make all the
components. Loral refused and said they would only be able
to produce the components that they had the low bid on.
Austin threatened to stop delivery on the components under the
original subcontract unless they got to make all 40 components in
the new contract and get a substantially higher price for all the
past and present components. Loral looked for another
supplier, but was eventually forced to acede to Austins
demands because otherwise they wouldnt have been able to
meet the Navys deadline. Austin sued Loral to recover
money still due on the second subcontract, but Loral also sued
Austin for the amount of the price increases, claimed they were
exacted illegally under duress and shouldnt be enforced.
The lower courts found for Austin, and Loral appealed to the
Court of Appeals of New York.
Procedure:
The two actions
were consolidated and, following a trial, the components supplier
was awarded the sum it requested and the supplier to the militarys
complaint was dismissed on the ground that it was not shown that
it could not have obtained the items in question from other
sources in time to meet its commitment to the Navy under the
first contract. On appeal, they found that there was
no disagreement of the facts, and that there were no serious
questions of law. The difficulty lies in the application of
the law to these facts.
Issue:
Whether a party
is permitted to hold the other party to the terms of the original
agreement in times of economic duress?
Holding:
No, The record
demonstrates that the military supplier agreed to the price
increases in consequence of the economic duress employed by the
component supplier and that there were no reasonable
alternatives, so they were forced to stay with that supplier!
Reasoning
(Rules):
*Why doesnt
the court talk about 2-209?
Rule:
A contract is voidable on the ground of duress when it is
established that the party making the claim was forced to agree
to it by means of a wrongful threat precluding the exercise of
his free will.
The court finds that what happened to Loral
is a classic case of economic duress. Austins
actions left Loral with no choice because its government contract
was so big and important.
The court feels that Loral met its burden of
showing that it couldnt get the parts from another
vendor. The court also feels Loral wasnt wrong in
waiting to sue until after the last delivery from Austin because
they feared reprisals.
The dissent argues that this is not a
question of law but a question of fact and the factfinder should
be given more deference. Furthermore, the dissent says that
there was a factual issue as to whether there were alternative
suppliers that Loral hadnt used before. Also, Loral
stated that they were rushing to close down the plant for
vacation time.
Economic Duress
Elements:
1)
The threat to withhold needed goods, unless
..
2) The
defendants threat was made in bad faith.
3) No
other practical alternatives for the plaintiff to obtain the
goods from another source w/in a reasonable time.
4)
The plaintiffs remedy at law would not be adequate.
(IN this case, Loral could have sued but they would have still
had to obtain the gears elsewhere).
Disposition:
The order was
modified with costs, and the military suppliers claim was
reversed in their favor.
|