|
Acme Mills &
Elevator Co. v. Johnson
141 Ky. 718 (1911)
Author: MadFlava13
Facts: In 1909, Johnson and Acme
Mills entered into a contract which stated that Johnson would
deliver 2,000 bushels of wheat at $1.03 per bushel (to be paid
upon delivery) to Acme Mills. Acme would provide sacks to Johnson
to transport the wheat from the thresher to the mill. Johnson
failed to deliver the wheat, and Acme sued to recover damages of
$320, including $80 for the value of the sacks provided to
Johnson.
Johnson admitted a
breach of contract, but denied that Acme was damaged. In
contracts of this type, the vendee is entitled to damages
against the vendor for a failure to comply and the measure of
damages is the difference between the contract price and the
market price of the property at the place and time of delivery.
Procedure: Acme Mills is suing
Johnson for damages equal to the wheat that was never delivered
and for the sacks provided for that delivery. The lower court
ruled for Johnson, with the exception of an $80 judgment for the
costs of the sacks.
Issue: As the value of wheat fell
below the value in the contract between the time of delivery and
the time of the agreement, was Acme still damaged by the breach
of contract?
Holding: The Kentucky Court of
Appeals affirmed the lower courts ruling, stating that
the appellant [Acme Mills], instead of being damaged by the
breach of the contract, was actually benefited to the extent of
about three cents per bushel.
Analysis: The court decided that a
breach of contract in a case involving the purchase and delivery
of goods would only be recognized if the vendee was damaged. In
essence, you can only sue for damages if the property is worth
the same or more than you agreed to pay. In this case, Acme Mills
would have been paying more than the wheat was worth, so the
court ruled Acme was not damaged by failure to collect the wheat.
(Johnson basically did them a favor by selling the wheat
elsewhere).
|