|
Ducolon Mechanical
Inc. v Shinstine/Forness Inc.
Washington Ct. of App. 1995
Author:- Sam
Biers
Facts: PL(Ducolon) a subcontractor won the
bid and was hired to install the plumbing, heating, ventilation,
and air conditioning within a new temple, for LDS Church, through
Shinstine. During the bid process Shinstine noticed Ducolon
that their bid may contained a mistake. All other bids were
substantially higher than Ducolon. Ducolon reviewed and
kept the existing bid without reviewing the bid calculations.
After Shinstine had extended the completion date, Ducolons
subcontract was terminated for defective work and remaining
behind schedule. Another company finished the work for
$16,000, half resulted from correcting Ducolons work.
Issue: 1)Whether Ducolon was entitled to
recovered the reasonable value of its services to Shinstine,
measured by the contract price minus Shinstines cost to
complete and repair.
Holding: Yes
Procedure: Trial ct. (bench) dismissed
materialmans lien, found Def wrongfully terminated
contract, and PL breached by delay. Neither party prevailed.
Affirmed.
Rule: The Party in breach is entitled to
restitution for any benefit that he has conferred by way of part
performance OR reliance in excess of the loss that he has caused
by his own breach.
Ct. Rationale: Shinstine election to
disaffirm the contract is irrelevant in calculating the value of
the benefit conferred to Shinstine prior to the breach of
Ducolon.Offsetting the award, under restitution, is appropriate
because the measurement is the benefit conferred to the
Shinstine.
PL A: Equitable relief in the form of
restitution PL should recover the actual amount of money spent in
the partial completion.
Def A: Pl should not be allowed to recover
an amount in excess of contract price, when Def, raised the bid
error and PL did not amend.
Verities- Facts
|