|
Cyberchron Corp v Calldata Systems
Development,Inc
US Court of appls 2nd circ 1995
Author: Meg
F
Cyberchron provided custom computer hardware. Calldata is
asubsidiary of Grumman Data Systems Corp. Grumman had a contract
w/ the MarineCorps to provide a system for a defense program
called ATACC. The equipmentconsists of a video processor, work
station, and monitor. Cyberchron attemptedto produce the
equipments via negotiations btwn parties. Cyberchron producedsome
of the equipment but none was ever delivered, nor was any payment
made.This lawsuit followed. The parties were not able to agree on
the weight of the eqpt.,and the penalties to be assessed against
Cyberchron for delivery of eqpt thatexceeded the contractually
agreed weight of 145 lbs. Cyberchron never agreed tothe terms of
the P.O. but commenced production non the less, w/
Grummanand Calldataâ™s encouragement (mid
July1990). No agreement was achieved andCalldata requested
Cyberchron to show cause w/I 10 days why the P.O. should notbe
terminated. Cyberchron responded in a detailed letter, but it was
rejectedbe Calldata in a letter in which Calldata âterminated
the POfor default effective immediately.â The distr
court found that Grumman hadcommenced negotiations w/ alternate
suppliers and entered into a contract w/another supplier whose
eqpt was supposedly inferior and weighed more aswell. No
enforceable contract had beenmade; however, Cyberchron was
entitled to recover for out of pocket expensessuch as material
and labor, and under the doctrine of promissory esstopel.
I
Although there was no contract btwn parties, can
Cyberchronrecover under the theory of promissory estoppel?
R
Yes, the injury inflicted upon Cyberchron was unconscionable,and
injustice can be avoided only by invoking the doctrine of
promissoryesstopel on Cyberchronâ™s behalf.
A
There are three elements here 1) a clear and unambiguouspromise
was made. 2) there was a reasonable and foreseeable reliance
thereon,& 3)an injury resulted, which could only be remedied
by invoking thedoctrine of prom/estop. Grumman putgreat
pressure on Cyberchron to proceed then abruptly terminated
thetransaction and began negotiations w/ another company who
produced inferior andheavier eqpt. Recovery should not be
extended to the period prior to July 1990.
CAffirmed judgment of dist. court re recovery on the theoryof
prom/estp but vacate and remand for determination of damages.
|